Ord Rd (west) caving in on corner (TOP 3)

Submitted on: May 14, 2025

Concern

West end of Ord Rd near empty lot is caving in on the side, and have a big plastic barrier. This should be shored ups and repaired before a mow cave-in causes an accident and block traffic.

Updates

March 21, 2023

Identified to Ministry PS

March 31, 2025

Identified as a ‘Top 3’ priority constituency issue to Minister Adams.

August 15, 2025

Requested update from Ministry.

October 15, 2025

This has been looked at by the Ministry and they have identified a design for fixing it. Work is delayed due to other larger and more critical cave-ins around the island.

January 18, 2026

Sent follow-up email to W&W PS and Minister requesting update.